Lagos-Calabar Coastal Highway: Works Minister, Others Lead NASS Committee on Inspection

In a bid to assure Nigerians of the quality and timely delivery of the recently commenced construction of the Lagos – Calabar Coastal Highway, .

The Minister of Works, David Umahi, Permanent Secretary, Adam Yakubu Kofarmata, Ph.D and other officials of the Ministry led members of the Senate and House Committees on Works to inspect and verify ongoing construction works on Sections I and II on Friday, 1st November, 2024.

In a statement issued on Friday, by Mohammed A. Ahmed, Director, Press and Public Relations, the Coastal Highway is one of four (4) legacy highway projects under the Renewed Hope Agenda of the present administration of His Excellency, Bola Ahmed Tinubu, GCFR.

It is an inter-state highway and economic corridor designed to traverse eight states along the coastal shoreline of the country starting from Lagos, South West and ending in Cross River State, South South, a total of 750 kilometres.

The contract, awarded to Messrs Hitech Construction Africa Limited, includes the construction of a continuously reinforced concrete pavement (CRCP) dual-carriage highway with accompanying drainages and culverts, median barriers, street lightings, and the relocation of public utilities like electric cables, poles, gas and water pipelines, as required and flagged-off on 24th May, 2024.

Section I of the project is 103 kilometres in length and falls entirely within the Lagos State border. However, a phased execution of the project was adopted, for ease of construction beginning with Phase 1 of Section I, which is 47.4 kilometres in length; Ch.0+000 (Ahmadu Bello Way Junction, Victoria Island) – Ch. 47+474 (Eleko Village Junction). Phase 1, Section II has a total length of 55.6 kilometres beginning from Ch. 47+474 – Ch. 103 + 000 (Ode – Omi, Lagos-Ogun Border.)

The tour of duty commenced at the beginning of Section I, where the Honourable Minister thanked the Members for the oversight visit, stating that they are witnesses to level of work carried out beneath the completed portion before applying cement.

According to him, decades of continuous dumping of refuse necessitated the removal of substantial quantities of unsuitable materials, underground.

Engr. Umahi informed them that plethora of court cases and petitions are slowing down the flow of work, while appealing to them to advise other Committees of the National Assembly to, always, liaise with them before summoning officials of the Ministry on frivolous matters concerning the project, also revealing that the Attorney General of the Federation and Minister of Justice had set up a legal team to deal with all pending cases in court.

The Minister advised aggrieved parties to stop playing politics with the viable project but approach the courts to seek redress like others, further divulging that Mr. President had, graciously, approved the payment of compensation to owners of properties within the project’s corridor, even to those with illegal structures.

“We have a lot of people who are not interested in this job being done. Everything government wants to do, some people want to thwart it,” he lamented.

On the Section II, he further informed the visiting legislators that the President had also given approval for the extension of the 7th Axial Road passing through the Dangote Refinery, Lekki Free Trade Zone and the Deep Sea Port, built by Messrs Dangote Industries, on Road Infrastructure Tax Credit Scheme, to be linked with the Coastal Highway. He went on to say that the two sections will be linked via a cable bridge, as obtained in other climes like Dubai, UAE.

The Deputy Director, Highways, Bridges and Design, Engr. Musa Seidu, FNSE briefed the entourage that work is going on, concurrently, at the two sections of the project.

This was collaborated by the Acting Federal Controller of Works, Lagos State, Engr. Olufemi Dare, who added that demolition of structures on the alignment had reached an advanced stage.

The Managing Director of the construction company, Mr. Dany Abboud assured the team of the availability of adequate manpower and state-of-the-art equipment to complete the project, in line with designed specifications and timelines, promising to take them on an inspection of their yard.

Speaking, on behalf of other members, the 10th Senate and its leadership, the Chairman, Senate Committee on Works, Sen. Mpigi Barinada disclosed that he was convinced that the project was at no point abandoned, as speculated by some mischievous Nigerians, while urging the Ministry not to hesitate in approaching them on any thorny issue concerning the project.

He appealed to the Minister to urgently consider the other sections of the highway passing through the Niger Delta, being an indigene of the zone.

Contributing, the Minority Whip of the Senate and a member of the Committee, Sen. Osita Ngwu prompted the Ministry to regularly update Nigerians about the pace of the project.

On his part, the Chairman, House Committee on Works, Hon. Akin Alabi pledged the commitment and support of members and the leadership of the House to seeing the successful and scheduled completion of the project.

He also appreciated and commended Mr. President for the legacy project, which will boost socioeconomic activities, as well as the Minister’s “can do spirit.”

Deputy Chief Whip of the Senate, Sen. Onyechachi Nwebonyi, applauded Mr President, the Minister and Contractor, insisting that the project will bring the economy back, as well as benefit Nigerians, tremendously. He dubbed it as “a game changer.”

Having seen it for themselves, they unanimously agreed that the 29th May, 2025 delivery day for Section I is certain, if not earlier.

LEAVE A REPLY

Please enter your comment!
Please enter your name here